Nirvaan Shah

Clarke Prize Environmental Design Challenge

BoxDrop

A cardboard return station for apartment lobbies.

January 2026 · Team of four · My role: station design, credit verification and costing

BoxDrop moves collection to the point of least friction, the lobby or mailroom, and closes the loop with a credit the resident can spend. The architecture has four parts: a station with a cutting tool, a barcode scanner and a sealed intake slot; a back end that logs each drop event against the scanned order; partner integration with delivery carriers, who buy the recovered cardboard and fund credits against future orders; and a resident app that holds the credit balance and an impact dashboard.

I worked on three of the four workstreams in a team of four. The footprint had to be slim and standardised to clear lobby fire-code circulation requirements. I also learned to design against misuse from the start, since an incentive system is only as good as the data that backs it.

From parcel pickup to cardboard return

The station needed to fit beside the mailboxes while leaving the lobby circulation route clear. The proposal brought three operations into a single unit: cutting and flattening the box, scanning its label, and depositing it through a sealed slot.

Team rendering of the blue BoxDrop station beside a wall of mailboxes, with a resident for scale.
Lobby concept rendering

What earns a credit?

A shipping label identifies an order. To earn a credit, a scan and a physical drop would have to register within the same time window. The proposal also included a daily cap and a fullness indicator so staff could service the station.

Team design slide identifying the guided cardboard cutter, scanner and intake on the proposed unit.
Two team mockups of the resident app showing a credit balance and an impact dashboard.

What would it cost?

I costed the system at $100K–$150K for app and server development, $1,500 per station to manufacture, $350 per station a year in maintenance, and about $30K a year in hosting.

Team financial plan with separate estimates for development, station manufacture, station maintenance and hosting.